NEW QUESTION 28
Should value in Adjusted Shipments Forecast measure always be equal to the Final Shipments Forecast measure?
- A. Yes,if the adjustment is made at the same aggregation level at which itis viewed, or below.
- B. Yes,if the demand plan is approved and values are locked.
- C. Yes, if the adjustment is made below the aggregation level at which it is viewed.
- D. Yes,if the demand plan hasn't been run again after adjustment.
- E. No, both measures will always be different.
Answer: A
NEW QUESTION 29
You are defining material planners for your organization. However, when you go to Manage Material Planners, your organization does not appear in the list of values. Why?
- A. The organization was not enabled for collection under Manage Planning Source Systems.
- B. You do not have data access to the organization.
- C. The organization must be enabled in Manage Planning Parameters.
- D. The organization is an Item Organization.
- E. The organization must be enabled in Manage Planning Profile Options.
Answer: A
NEW QUESTION 30
You want to be able to filter your data by the planner code attribute on the item. Where can you go to do this?
- A. The process "Add Levels and Attributes" must be run to associate new attributes.
- B. Configure Planning Analytics > Measure Catalog
- C. Enable planner code on Planning Analytics page.
- D. Configure Planning Analytics > Levels and Attributes tab
- E. The process "Associate Measure Catalog Attributes" must be run to associate new attributes.
Answer: C
NEW QUESTION 31
Where do you view the collected data for Organizations, Customers, Suppliers, Carriers, and Interlocation Shipping Networks?
- A. View Simulation Sets
- B. Review Plan Inputs
- C. Maintain Supply Network Model
- D. Planning Analytics
- E. View Collected Data
Answer: C
NEW QUESTION 32
Which statement applies only to the planning of back-to-back items and not standard items?
- A. Must have added sourcing rules to the Global Order Promising assignment set.
- B. Planning analyzes supply shortages and capacity overloads using any of the standard planning tools.
- C. Planning collects bookings or shipments history to forecast items.
- D. Planning pegs reserved supplies to sales orders.
- E. Must use Global Order Promising and Supply Chain Orchestration to release and create new supplies
Answer: E
Explanation:
NEW QUESTION 33
Your client has operations in the west coast of the US. If the customer is in the western half of the US, then they would like to ship the product from their warehouses. If it's in the eastern half of the US, then they want to drop ship it from a supplier.
How would you recommend they set the assignment up?
- A. Set up a region for the west coast warehouse and an item-region level assignment for the drop ship.
- B. Set up an item-organization assignment for the west coast warehouse and an item-organization level assignment for the drop ship.
- C. Set up an item-region assignment for the west coast warehouse and a region level assignment for the drop ship.
- D. Set up two region level assignments, one for the west coast and the other for the east coast.
- E. Set up by each customer for the customers who should get product from each warehouse.
Answer: A
NEW QUESTION 34
Another planner has previously created a supply plan, but you now need to make some changes so that you can do some 'what-if' analysis. How can you go about duplicating this plan?
- A. Run process "Duplicate supply plans" with existing plan as parameter.
- B. Manage Plans > Search and select supply plan > Actions > Edit Plan Options > Select Copy.
- C. You cannot duplicate a plan that is not owned by you.
- D. You cannot duplicate plans. You must create a completely new supply plan.
- E. Manage Plans > Search and select supply plan > Actions > Duplicate.
Answer: E
NEW QUESTION 35
Which KPIs are available to measure forecasting accuracy and specify how these measures aggregated from item-organization level to higher levels.
- A. MAPE, MAD, and Bias are used to measure forecast accuracy. MAD and Bias are aggregated using sum. MAPE is aggregated using weighted average.
- B. MAPE, MFE, and Bias are used to measure forecast accuracy. MAPE and MFE are aggregated using weighted average. Bias is aggregated using sum.
- C. MAPE, MAD, and Bias are used to measure forecast accuracy. MAPE and Bias are aggregated using weighted average. MAD is aggregated using sum.
- D. MAPE, MFE, and Bias are used to measure forecast accuracy. MAPE and Bias are aggregated using weighted average. MFE is aggregated using sum.
Answer: A
NEW QUESTION 36
During a client implementation, it is determined that an external forecast will need to be imported into Planning Central for use as a Demand Schedule in a Supply Plan.
What three steps must be executed to enable the successful load of the External Forecast file? (Choose three.)
- A. Collect Planning Data Process must be run from Planning.
- B. Load Interface File for Import Process must be run.
- C. Collect Legacy Data Process must be run from Planning.
- D. Flat File must be zipped.
- E. CSV file must be generated.
Answer: B,C,E
NEW QUESTION 37
Your client has made a change to item costs. What type of collection do they need to run to only pick up this change?
- A. Item costs is automatically updated. No data collection is necessary.
- B. Must run full data collection. It is not possible to update just item costs.
- C. Run net change collection for item costs.
- D. Item costs cannot be updated via a data collection processes.
- E. Run targeted collection for item costs.
Answer: E
NEW QUESTION 38
Your customer wants to display a numeric measure in both pound and kilogram Units of Measure (UOM) on a table. Describe the configuration steps to display a measure in two UOMs.
- A. Open a table and select Actions, View Table Configuration and click Measure tab. Find the measure, duplicate the measure, and rename it. Now select pound as UOM for the original measure and kilogram as UOM for the duplicated measure.
- B. Open a table and select Actions, View Table Configuration and click UOM tab. Select primary UOM as pound and secondary UOM as kilogram.
- C. Open a table and select View, Format Measures to find the measure. Now select pound as primary UOM and kilogram as secondary UOM.
- D. Open a table and select View, Format Measures to find the measure. Duplicate the measure and rename it. Now select pound as UOM for the original measure and kilogram as UOM for the duplicated measure.
Answer: C
NEW QUESTION 39
Identify two ways you can track performance against goals when defining measure goals. (Choose two.)
- A. Specification
- B. Range
- C. Quantity
- D. Value
- E. Aggregation
- F. Attribute
Answer: D,F
NEW QUESTION 40
Demand planner opens the pre-seeded plan summary of the demand plan and wants to analyze the forecast results. Describe the steps to review and analyze the forecast results.
- A. Click "Demand at Risk in thousands" tile. Review "Demand at Risk by Product Category" graph and pick a product category. Right-click on product category, click Drill To -> Default Group -> Demand Analysis to open the table and review the details.
- B. Click "Revenue and Margin" tile. Review the "Revenue by Period" graph and pick a specific period. Right-click on a period, click Drill To -> Default Group -> Revenue Analysis to open the table and review the details.
- C. Click "Forecast Comparison in the thousands" tile. Review "Forecast Comparison by Product Category" graph and pick a product category. Right-click on product category, click Drill To -> Default Group -> Forecast Analysis to open the table and review the details.
- D. Click "Revenue and Forecast" tile. Review "Revenue by Period" graph and pick a specific period. Right-click on a period, click Drill To -> Default Group -> Forecast Analysis to open the table and review the details.
Answer: C
Explanation:
NEW QUESTION 41
Your client has a requirement to restrict Supply Plan data access. Identify three Data Access Set detail entities that can be used to restrict plan data access. (Choose three.)
- A. Customer
- B. Supplier
- C. Transaction Type
- D. Material Planner
- E. Item
- F. Demand Class
Answer: A,B,E
Explanation:
NEW QUESTION 42
You have executed Planning Data Collection and want to confirm that data has successfully been collected. Identify the three data combinations that can be viewed using the Maintain Supply Network Model Page. (Choose three.)
- A. Supplier Site and Service Level
- B. Safety Stock and Subinventories
- C. Sales Channel and Demand Class
- D. Calendar and Master Organization
- E. Customer Location and Carriers
Answer: A,D,E
NEW QUESTION 43
During an implementation, customer is in the process of planning supply requirements. Customer also needs to generate forecast and safety stock levels. Which plan type on the plan options should the customer be running?
- A. Safety Stock and Forecast Plan
- B. Integrated Plan
- C. Demand and Supply Plan
- D. Demand Plan
- E. Supply Plan
Answer: C
NEW QUESTION 44
Which option outlines changes you can make to a simulation plan when evaluating demand and supply?
- A. Change item specification values, change item lead times, create mass changes for items all at once, change item-organization specification values
- B. Add demands, cancel demands, reschedule demands, add new planned orders, reschedule supplies
- C. Add demands, cancel demands, reschedule demands, add supply, cancel supply, reschedule supplies
- D. Change item specification values, change item lead times, create mass changes for items
- E. Change item specification values, change item lead times, change item-organization specification values
Answer: C
NEW QUESTION 45
You ran a demand plan and you are reviewing the shipments forecast value measure. It is always zero for a particular item. Identify the root cause of this problem.
- A. In plan parameters, shipment forecast value measure expression is not defined.
- B. In planning measures catalog, shipment forecast measure is not enabled at item and organization level.
- C. In plan parameters, Item List Price marked as primary does not have price defined for the particular item.
- D. In planning measures catalog, shipment forecast value measure is not enabled at item and organization level.
Answer: D
NEW QUESTION 46
Your customer wants to be able to manually change the input values in purchase orders and transfer orders for the suggested plan recommendations. Which two recommendations are released by supply chain planning to Oracle Supply Chain Orchestration Cloud? (Choose two.)
- A. Reschedules of sales orders, make, and buy
- B. New planned orders for make, buy, and transfer of supplies
- C. Reschedules of existing make, buy, and transfer supplies
- D. Schedule planned orders for make, buy, and transfer of supplies
Answer: B,C
NEW QUESTION 47
......
Oracle 1z0-1066-22 Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|
| Topic 5 |
|
Test Engine to Practice 1z0-1066-22 Test Questions: https://examsboost.pass4training.com/1z0-1066-22-test-questions.html